![]() |
||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||
|
On April 16, 1996, a storm categorized as a 50-year event, hit the New Haven area. Heavy rainfall raised the volume and speed of the West River. The resulting scouring! action undermined the eastern pier foundation, causing the bridge to give way. Due to the failure of the main pier support, the bridge was closed to traffic. A DEPRESSION-ERA
PROJECT Though not technologically significant, the new bridge was more aesthetically pleasing than the mundane structure it replaced. It included art deco-style detailing such as stepped forms at the end of parapet railings and fluting on the outside of the parapets. It was a three-span, reinforced concrete T! -beam system, 95-ft long and 45-ft wide. Three 28-ft spans were supported on reinforced concrete abutments and piers. The overall bridge width carried two lanes of Blake Street traffic over a 30-ft roadway, with two six-ft sidewalks and 1.5-ft parapets on both sides. The river channel was severely skewed at the north inlet side of the bridge and caused a heavy build-up of silt and vegetation at the west span. As a result, the center and east spans had been channeling most of the river's flow, and it was the east pier that failed. In 1990, as part of its flood-control project, the U.S. Army Corps of Engineers constructed several new features in the vicinity of the bridge, including an earth berm that would later be used as a temporary roadway during the reconstruction project. The closing of the bridge created significant problems. The Blake Street corridor serves as an important transportation artery in the area, carrying more than 10,! 000 vehicles a day. With the bridge out of service, traffic patterns were adversely affected, causing disruption delays for emergency services in New Haven's Westville community. The extensive commercial development within the corridor made the reopening of the bridge critical to local businesses. New Haven Mayor John DeStefano, Jr., declared a bridge emergency on April 29, 1996, which set the replacement project on a fast-track course. TWO-PHASE
REPLACEMENT PROJECT Phase I consisted of the design and construction of a temporary bridge, including demolition of the existing structure, to be completed as soon as possible with emergency funding from CDOT. Phase II would follow with the design and construction of the permanent bridge. The Phase I project, which also included a temporary roadway approach, would restore traffic in a timely manner and allow the permanent! bridge to be constructed without impeding the flow of traffic. The temporary bridge was a 101-ft, single-span Acrow Corporation of America (Carlstadt, NJ) panel structure. The structure, which had been used on previous projects, was disassembled in storage, and thus was quick and simple to construct. The project retrofitted the bridge to include a sidewalk on the north side, which allowed pedestrian movement to be maintained between the residential neighborhoods east of the bridge and the Westville section. Utility pipe hanger supports were used to buttress an eight-in, diameter water main and a natural gas main of the same dimensions. Concrete abutments were designed to incorporate the required flood-control structure elevations established by the Army Corps of Engineers' flood-control project. An unexpected construction obstacle was encountered when contaminated soil was discovered during excavation for the western abutments and roadway approach. To minimize interference with the Phase I construction schedule, as much contaminated soil as possible was left in place and the top layer was covered with geotextile fabric. All of the impacted contaminated soil was removed when the permanent bridge was put in place. The temporary roadway approach east of the bridge was constructed on the earth dike that was part of the earlier flood-control project. The dike consisted of precast interlocking concrete block slope protection that was reconstructed as part of the temporary access roadway on the east approach. The removal and replacement of the interlocking concrete blocks was accomplished mostly by hand. MINIMIZING
IMPACT ON BUSINESS The permanent bridge, which has been open for about a year, is 96 ft long and 45 ft wide. It carries two lanes of Blake Street traffic over a 30-ft roadway, with two six-ft sidewalks and 1.5-ft parapets on each side. The three-span structure was replaced with this single-span structure, eliminating piers in the water. The bridge superstructure is supported by prestressed deck units. All units are 3.3 ft deep, with eight units having a nominal 36-in, width and four units with a nomi! nal 48-in, width. A 12-in, water main is supported under the sidewalk on one side of the bridge, and 12-in, and six-in, natural gas pipelines are supported under the sidewalk on the other side. Pipelines are located in spaces between pre-stressed deck units, with channel supports welded to steel anchors set in pre-stressed deck units. Telephone conduit is located in the concrete sidewalk. The bridge parapet system consists of two square tubular metal bridge rails located between concrete posts. A low-flow fish channel was created because the Connecticut Department of Environmental Protection and the National Marine Fisheries Service were concerned about interfering with the seasonal movement of migratory fish and the need to preserve fish spawning and nursery habitats in the West River. Although construction of the permanent bridge was delayed more than a year due to lack of funding, the temporary structure kept traffic flowing and pro! vided ready access to businesses in the area. Total construction cost of the project was approximately $2 million. Roger A. Krahn, P.E. |
||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||