Bill Killeen, President of Acrow Corporation, received an emergency call from the NJDOT requesting to meet at the accident scene that afternoon. At the accident scene he was able to assess the requirements for a temporary bridge and commit to supplying steel components for a 90 foot long by 30 foot wide crossing over the damaged structure. Early Saturday morning
Acrow’s engineers designed the temporary bridge while operations staff
organized the inventory of steel components and loaded trucks for
delivery. By 1pm Saturday afternoon, 17 hours after being given the
go-ahead by the NJDOT, the Acrow® Working closely with the NJDOT and contractors on a 24 hour cycle over the weekend, the Acrow bridge was built and is scheduled to open Wednesday June 27th for regular motorist traffic. Bill Killeen made the following comment, “The Acrow bridge will provide two lanes of traffic on Interstate 80 westbound as permanent reconstruction of the damaged bridge is completed during the summer months”. He further added, “ It was especially rewarding for the Acrow team to assist the NJDOT and the metro area motorists after this most serious and paralyzing road closure”. Acrow Corporation is
a international bridge engineering and supply company servicing the
transportation and construction industry for over 50 years with a
full line of steel bridge products for vehicle and pedestrian applications. |
||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||